AI data centres in the Middle East and North Africa

Energy, water and cost: what is being built, what it takes, what it costs, where the numbers disagree, and the experts to ask.

Prepared by Rawad and our team at the request of Ricardo Khoury. Every figure carries a numbered source in the full briefing.

The short answer

Three questions, three answers

2%

Energy: small today, growing fast

UAE data centres used about 2% of the country's electricity in 2025. In Saudi Arabia the share could reach 2.8% to 11.6% by 2030, depending on how much AI is built. [4, 18]

70%+

Water: a security question

Most Gulf countries get 70% or more of their drinking water from desalination. Most of a data centre's water is used off site, in making its electricity. [5, 9, 11]

$9.20/W

Cost: cheapest to build, debated overall

Building costs about $9.20 per watt in the UAE, against $12 to $13 in Europe, Asia and North America. One study finds the total cost similar to the US. [14, 20]

North Africa is at an earlier stage, with tighter power and water: Egypt has about 60 MW of data centres running, Morocco 1.5 MW. [37, 40]

Numbers in brackets refer to the source list of the full briefing.

1 · What is being built

Announced is far larger than what runs

Operational, 2024290 MW
Operational, Q1 2026476 MW
HUMAIN target, 20301,900 MW
NEOM Oxagon (planned)1,500 MW
HUMAIN target, 20346,600 MW

Saudi Arabia, capacity in megawatts

The region's third-party capacity is about 500 MW today, forecast at about 1.5 GW by 2030. [16]

The UAE and Saudi Arabia add 2 to 3 GW by 2030, still under 2% of the world's data-centre power. [13]

Egypt runs about 60 MW and Morocco 1.5 MW, against plans of hundreds of megawatts. [37, 40]

Sources: KAPSARC [4]; Deloitte [15]; Informa [16]; S&P Global [13]; Enterprise [40]; BMI (Fitch Solutions) [37].

2 · Energy

The world's data centres are doubling their electricity use

2024415 TWh
2025 (about +17%)485 TWh
2030, IEA base case945 TWh
2035, IEA base case1,200 TWh

World data-centre electricity use, terawatt-hours

About 1.5% of the world's electricity in 2024, just under 3% by 2030. [1]

AI-focused data centres grow fastest: their electricity use triples. [2]

The US (45%), China (25%) and Europe (15%) use most of it today. [1]

Source: IEA, Energy and AI (2025) and Key Questions on Energy and AI (2026) [1, 2]. 2025 = 415 TWh plus 17%.

2 · Energy

What it means for Gulf grids

UAE: about 173 TWh of electricity in 2025, of which data centres took about 3 TWh (2%); about 6 TWh expected by 2030. [17, 18] Saudi Arabia: 2.8 TWh in 2024 (0.85%). By 2030, KAPSARC's three scenarios: [4]

KAPSARC scenario, 2030CapacityElectricityShare of national demandWith efficiency measures
Baseline (little AI)about 1,050 MW10.16 TWh2.79%—
Moderate growthabout 2,000 MW20.15 TWh—17.62 TWh
High growthabout 4,100 MW42.23 TWh11.55%36.76 TWh

Efficiency measures cut demand by about 13%. Emissions in 2030 range from 5.8 to 24.0 Mt of CO₂ on a fossil grid; meeting the 50% renewables target cuts that by about 68%. [4]

Sources: KAPSARC, December 2025 [4]; The National (Wood Mackenzie figures) [18]; Informa [17].

2 · Energy

Heat costs energy

1.5

Saudi data centres today

Average PUE, range 1.5 to 1.8: the total electricity a site needs for each unit its computers use. [4]

1.1

AI sites in cool climates

The best recorded value is 1.028. Cooling takes from about 7% of a site's electricity to over 30%. [1, 4]

+35–65%

More electricity in the Gulf

For the same computing, at a PUE of 1.5 to 1.8 against 1.1. Our calculation.

Where the power comes from: UAE renewables grew 117% from 2022 to 2025, to more than 7.7 GW, with a target of over 23 GW by 2031; Saudi Arabia targets 50% renewables. KAPSARC still finds Saudi Arabia cost-competitive at a PUE of 1.6 to 1.8. [4, 5]

Sources: KAPSARC [4]; IEA [1]; UAE Crosscurrents report [5]. “Our calculation” = our arithmetic from published figures.

3 · Water

Most of a data centre's water is not used on site

~50%

Making its electricity

Thermal power plants need cooling water. The World Economic Forum puts 72% of a data centre's water consumption off site. [5, 9]

~30%

Cooling on site

Chilled air, or cold treated water through plates on the chips. Evaporative cooling uses 1 to 3 m³ per MWh of computing, most in the hot months. [5, 9, 11]

The rest

Fuel, chips and building

Chip making is especially water-intensive; building large sites uses fresh water for concrete, dust control and cooling systems. [5, 11]

The Gulf difference. Gulf power plants are mostly cooled with seawater, which is not in short supply. [11] What matters here is the fresh water used for cooling on site, which usually comes from desalination or from treated wastewater.

Sources: UAE Crosscurrents report, with Eurasia Group [5]; World Economic Forum [9]; Enterprise [11].

3 · Water

Why the published numbers differ about twenty times

Direct cooling only (Rystad)644 bn L
Cooling + power + chips (IEA)1,200 bn L
Wider footprint (UAE report, UN University)9,320 bn L

Data-centre water worldwide in 2030, billion litres: the same question, three scopes

Today: 222 billion litres for direct cooling (2025), 560 billion with power and chips (2023), 4.5 trillion as a full footprint (2025). [5, 7, 11]

Ask any expert which one they mean.

Sources: Rystad Energy [7, 8]; IEA via Enterprise [11]; UAE Crosscurrents report [5]; UN University [6].

3 · Water

In the Gulf the water risk is security, not price

Desalination

Most Gulf countries rely on it for 70% or more of their drinking water. [11]

Capacity

MENA hosts over 40% of the world's desalination capacity, the GCC alone 33%. [29]

Security

Iranian strikes have hit desalination plants in Bahrain and Kuwait during the Iran war. [11]

Exposure

Nearly 40% of identified AI capacity worldwide is in areas of high or extremely high water stress. [3]

Real operator data

Khazna (UAE) used about 393,000 m³ in 2025; its DXB1 site is cooled with treated sewage effluent. [12]

Hot days

Evaporative cooling water can spike six to ten times above average on the hottest days. [23]

Market estimates

UAE 24 to 61 billion litres, Saudi 20 to 88 billion (2025 to 2030): far above Khazna's figures, unverified. [11]

Planning

The UAE's report finds MENA has the highest projected water stress for 2030. [5]

Sources: Enterprise [11]; IEA [3, 29]; Khaleej Times (Khazna ESG report) [12]; UC Riverside [23]; UAE Crosscurrents report [5].

3 · Water

The cooling trade-off: water or electricity

Dry cooling

  • Saves about 2.15 litres of water per kWh of computing
  • Needs an extra 0.30 to 0.74 kWh of electricity to do it [8]

Desalinated water

  • Desalinating those 2.15 litres takes about 0.003 to 0.011 kWh
  • At 1.55 kWh/m³ (Saudi record) to 5 kWh/m³ (conventional) [27]
30 to 220×

less electricity to cool with desalinated water than with dry cooling, measured in energy alone (our calculation). In the Gulf the case against water cooling is about water security, peak demand and brine, not energy.

Sources: Rystad Energy [8]; Zawya [27]; UAE Crosscurrents report [5].

3 · Water

What is already being done

Treated wastewater

Qatar and other GCC countries show major cooling can run on non-potable water; about 82% of the region's wastewater is never collected or treated. [24]

Liquid cooling

Gulf operators are testing systems that could cut cooling water by up to 90%; Khazna's planned 100 MW site in Ajman cools direct to the chip. [12, 24]

Planning

The UAE's report proposes a voluntary global declaration: permits tied to local water and energy, transparent reporting, water risk in siting. [5]

The UN Water Conference, co-hosted by the UAE, meets in Abu Dhabi on 8 to 10 December 2026. [5]

Sources: IWMI via Arab News [24]; Khaleej Times [12]; UAE Crosscurrents report [5].

4 · Cost

Building is cheapest in the Middle East

Tokyo (most expensive)$18.28/W
Europe, average$12.76/W
Asia, average$12.10/W
North America, average$12.06/W
Saudi Arabia$10.80/W
Qatar$9.80/W
UAE$9.20/W
Middle East, average$9.93/W

Construction cost, 2026, US$ per watt

451 Research: about $11 million per MW in the UAE and $13 million in Saudi Arabia, against $12 million in Europe and $13 million in North America. [13]

That is the building. The computers cost more: about $20 million per MW (our calculation from [21]).

Sources: Turner & Townsend Construction Cost Index 2026 [14]; S&P Global, 451 Research [13]; SemiAnalysis [21].

4 · Cost · our calculation

One megawatt of computing in the Gulf, for one year

Electricity1 MW × 8,760 hours × PUE 1.5 = about 13,140 MWh [4]
Electricity billAt $48 to $53 per MWh: about $630,000 to $700,000 a year [4]
Cooling water, if evaporativeAbout 9 to 26 million litres (1 to 3 m³ per MWh) [9]; KAPSARC uses 25 to 30 million [4]
Energy to desalinate itAbout 14 to 150 MWh: 0.1% to 1.1% of the site's electricity [27]
Price of that waterAbout $2,400 to $16,000 a year, at Gulf desalination tariffs of $0.28 to $0.53 per m³ [25, 26]
Building, onceAbout $9 to $13 million; the computers about $20 million [13, 14, 21]

For an operator, water is cheap and electricity is the main running cost. For the country, the question is where the water comes from and how secure that supply is.

Industrial electricity costs about $0.05 to $0.07 per kWh in Riyadh and Abu Dhabi [19]. Sources as numbered.

4 · Cost

The money, and the counter-view

The money

  • The UAE and Saudi Arabia: more than $100 billion committed to AI and technology [11]
  • Stargate UAE: up to $10 billion; Microsoft: $15.2 billion in UAE data centres since 2023 [17]
  • GCC AI data centres: $5 to $7 billion in 2026 alone [22]
  • WEF with Bain: more than $1 trillion of value across MENA by 2030 [10]

The counter-view

  • A December 2025 study finds the total cost of a 100 MW data centre similar in the US and the UAE; it calls its figures provisional [20]
  • It sees subsidies, business opportunities or hedging, not cost, behind the interest [20]
  • KAPSARC: how fully the machines are used matters more than the electricity price; one source finds Saudi costs up to 30% lower [4]

Sources: Enterprise [11]; Informa [17]; Analysys Mason [22]; World Economic Forum [10]; Centre for the Governance of AI [20]; KAPSARC [4].

5 · North Africa

Egypt and Morocco: an earlier stage, tighter power and water

EgyptMorocco
Running14 data centres, about 60 MW [40]; about 20 MW of new capacity firmly committed [39]14 data centres, 1.5 MW in operation (Q2 2026); 140 MW under construction, 400 MW planned [37]
AnnouncedPlans of 400 to 500 MW, not yet funded; up to 200 MW for $1 billion (Vodafone, Elsewedy, Cassava); up to 192 MW for $2.1 billion (Gulf Data Hub, Elsewedy) [39]Iozera, Tetouan, 386 MW [37]; Igoudar Dakhla, 500 MW green campus, studies launched April 2026 [54]
ElectricityGas made 81% of the power mix in 2024 [42], increasingly imported [39]; power cuts to ration gas from July 2023 [46]; renewables target 45% by 2028 [44]Coal 58% of electricity in 2025, 52% by 2030 (IEA figures) [50]; renewables 46.1% of installed capacity [51]; grid limits slow projects [37]
WaterAbout 500 m³ per person a year, half the UN water-poverty line; demand 88.55 billion m³ against 65.35 billion renewable [47]; the Nile gives over 98% [48]Desalination gives 25% of drinking water, 60% targeted by 2030 [52]; the Casablanca plant due in February 2027 [53]

Sources as numbered in the full briefing, section 5. Not covered: Algeria, Tunisia, Libya.

5 · North Africa · our calculation

What the announced projects would mean

2–2.5%

of Egypt's electricity

400 to 500 MW run all year at a PUE of 1.5: about 5.3 to 6.6 TWh, against 263 TWh planned for 2026/27, today mostly from gas. [42, 45]

5–6%

of Morocco's installed capacity

A 500 MW campus needs about 600 to 750 MW of supply. On the grid most power is coal, so its emissions depend on its own renewable supply. [37, 50, 51]

<0.01%

of Egypt's water demand

A 100 MW site with evaporative cooling: about 0.9 to 2.6 million m³ a year. The question is local: where it draws its water, on the hottest days. [9, 23, 47]

“Our calculation” = our arithmetic from the published figures cited.

6 · Risks and open questions

What could go wrong

Capacity may not arrive

The gap between announced and running is large; KAPSARC advises sequencing to avoid stranded assets. [4, 15, 16]

Water security

Dependence on desalination, and strikes on desalination plants during the Iran war. [11]

Peak demand

Cooling water and electricity both peak on the hottest days; AI loads can spike sharply. [10, 23]

Weak data

No standard measure for water; estimates differ about twenty times. The UAE's report asks for comparable reporting. [5]

North African grids

Grid limits slow projects in Casablanca; Egypt rationed power in 2023 to save gas. [37, 46]

Emissions

Saudi data centres could emit up to 24 Mt of CO₂ in 2030 on a fossil grid, about 7.7 Mt with 50% renewables. [4]

Public acceptance

In the US, 75 projects worth about $130 billion were blocked or delayed in Q1 2026, often over water and power. [9]

No formal plans yet

Public statements by UAE and Saudi officials on water have not included formal plans for data-centre water use. [11]

Sources as numbered in the full briefing, section 6.

For the research

Start here: the studies to read first

1

IEA, Energy and AI (2025) and Key Questions (2026). The world baseline and scenarios to 2035. [1, 2]

2

IEA, Powering Artificial Intelligence (2026). AI capacity against water stress; water used in power. [3]

3

KAPSARC, AI and Energy: The Future of Data Centers in Saudi Arabia (Dec 2025). The most detailed national study in the region. [4]

4

UAE Mission to the UN with Eurasia Group, Crosscurrents (Oct 2026). The AI, water and energy link, with five recommendations. [5]

5

UN University (UNU-INWEH), Environmental Cost of AI's Energy Use (June 2026). Carbon, water and land footprints by electricity source. [6]

6

Turner & Townsend, Data Centre Construction Cost Index (2026). Build cost, market by market. [14]

7

North Africa: BMI (Fitch Solutions) on Morocco (June 2026); Enterprise on Egypt (Sept and Oct 2026). Running and announced capacity. [37, 39, 40]

Every link is in the source list of the full briefing.

7 · The experts to ask

Researchers and institutions

Prof. Kaveh Madani

Director, UN University Institute for Water, Environment and Health

Led the June 2026 UN report on the carbon, water and land footprint of AI's electricity; 2026 Stockholm Water Prize laureate. [6]

unu.edu/inweh

Dr. Miriam Aczel

Researcher, UNU-INWEH

Lead author of the same report: methods, and the trade-offs between carbon, water and land. [6]

unu.edu/inweh

Prof. Shaolei Ren

UC Riverside

A leading researcher on AI's water footprint, including peak-day water demand. [23]

Email published on his papers

Khaled Alshehri

Fellow, KAPSARC (Riyadh)

Lead author of the most detailed public study of Saudi data-centre energy, emissions and cost. [4]

kapsarc.org

Nick Kraft

Senior Analyst, Water and Agriculture, Eurasia Group

Led the research behind the UAE's Crosscurrents report (Oct 2026). [5]

Eurasia Group

IEA Energy and AI team

International Energy Agency, Paris

Authors of the reference global studies, including AI capacity in water-stressed areas. [1, 2, 3]

iea.org

Youssef Brouziyne

Regional representative for MENA, IWMI

Co-author on MENA's water reality for AI; IWMI works with Saudi Arabia on treated-water reuse. [24]

IWMI

We do not know them personally: the routes shown are their public institutional channels.

7 · The experts to ask

Policy, industry and operators

Jessica Obeid

Founding partner, New Energy Consult (Dubai)

Energy engineer and policy consultant, formerly at Chatham House and UNDP in Beirut, on how sustainably the Gulf can power and cool data centres. [11, 34]

New Energy Consult; WEF profile

Dr. Naser Alsayed

Gulf water and energy policy researcher

Writes on Gulf water security for AGSI and MEI; quoted as senior fellow at the Fiker Institute, Dubai. [11, 35]

AGSI; Fiker Institute

Mohammed Soliman

Senior fellow, Middle East Institute

Technology and geopolitics in the region; quoted on the physical limits of the Gulf's data-centre boom. [36, 38]

mei.edu

Dr. Minh Khoi Le

Global Head of Data Center and Hydrogen Research, Rystad Energy

Built the global model of data-centre cooling water and the dry-cooling trade-off. [7, 8]

Rystad Energy

Alan Coary

Data Centre lead, Middle East, Turner & Townsend

Construction cost of data centres in the region. [14]

Turner & Townsend

Elisabetta Baronio

ESG Director, Khazna Data Centers (UAE)

The operator side: published water, energy and climate-risk data for UAE sites. [12]

Khazna Data Centers

Karikari Achireko

Africa Sustainable Energy Centre (ASEC)

Wrote for the World Economic Forum on whether Africa's power grids are ready for AI data centres. [55]

ASEC; World Economic Forum

We do not know them personally: the routes shown are their public institutional channels.

7 · The experts to ask

Questions worth putting to them

1

Which water figure do you use, and why?

Direct cooling, consumption including power, or the full footprint.

2

For a Gulf site, which cooling is better overall?

Evaporative with desalinated or treated water, against dry or liquid cooling.

3

How much of the announced capacity will run by 2030?

4

What share of national electricity and desalinated water could data centres take, country by country?

5

Which rules on water reporting, siting or tariffs are coming in the region?

6

In Egypt and Morocco, where would the power and cooling water come from?

The full briefing

Every figure, every source

12 pages, 55 numbered sources and 14 experts with the reason to ask each one.

Prepared by Rawad and our team at the request of Ricardo Khoury, 24 November 2026, from published sources. Where the sources disagree, both are shown; our own arithmetic is marked “our calculation”.